Kabkabiya Water Station

Kabkabiya Water Station

The project is a full water station in the village that includes:

1-  Well drilling 100 feet deep.

2-  Provision and installation of steel Elevated Tank with size of 10,000 Gallon.

3-  Provision and installation of (Hybrid pumping System (Solar & Diesel Unites )  & the Submersible pump.

4-  Fencing & Internal distribution network ( Animal basin and Karo hose and human drinking tabs).

Hay Al-Sham Block 29 Water Station

Hay Al-Sham Block 29 Water Station

The project is a full water station in the village that includes:

  • Drilling of an underground well 700 feet deep.
  • Installing a 24 m3 GRP water tank on a 6 -meter high iron rack
  • Installing a solar water pumping system.
  • Fencing and stripes for the station

The number of project beneficiaries is about 8000 residents, in addition to livestock.

Kalinj Water Station

Kalinj Water Station

The project is a complementation of a water station in the village that includes:

  • Installing a 12 m3 GRP water tank on a 6 -meter high iron rack
  • Installing a solar water pumping system.
  • Fencing and stripes for the station

The number of project beneficiaries is about 4000 residents, in addition to livestock.

ِAl-Layona Water Station

ِAl-Layona Water Station

The project is a complementation of a water station in the village that includes:

  • Installing a solar water pumping system.
  • Fencing and stripes for the station

The number of project beneficiaries is about 6000 residents, in addition to livestock.

Hamooda Water Station

Hamooda Water Station

The project is a water station in the village that includes:

  • Drilling of an underground well 550 feet deep
  • Installing a 24 m3 GRP water tank on a 6 -meter high iron rack
  • Installing a solar water pumping system.
  • Fencing and stripes for the station

The number of project beneficiaries is about 15000 residents, in addition to livestock.

Bara Water Station

Bara Water Station

The project is a water station in the village that includes:

  • Digging an underground well 1100 feet deep
  • Installing an electric water pumping system.
  • Fencing and stripes for the station

The number of project beneficiaries is about 6000 residents, in addition to livestock.