Mesiktab Village Water Transmission Line

Mesiktab Village Water Transmission Line

The project consists of supplying, drilling, and installing a water transmission line in the village with a total length of 5856 meters distributed between 8 inches and 6 inches and 4 inches, to distribute within the existing stations, more than 7 stations can be linked to the transmission line and the internal network and the work of a central station that contains a ground and upper tank, pumping units and a tracking system.

 The project's goal: 

Provide water for the residents of Al-Maskitab village north and to sustain the water. The number of the beneficiaries of the project is about 2100 families, or about 12,000 people, for the villages of Al-Maskitab, and the Animal wealth estimated at more than 2000 heads.

AlNakhiel Water Station (Dar Al Salam Square 81) Hameshkoreb

AlNakhiel Water Station (Dar Al Salam Square 81) Hameshkoreb

The project is a complete water station in the area. Sadagaat Charity Organization has drilled a 610 depth underground well and installed a solar water pumping system (submersible pump and solar panels with a support structure and control switch).

 In addition to installing a 24 cubic meter GRP water tank on an iron stand with a height of 6 meters and building a complete fence for the station and a well-operating system. 

The number of beneficiaries of the project is about 11,000 residents of the area and an additional number of residents of the neighboring areas of more than 5,000 families. 

 The implementation was carried out by contractors specialized in drilling, tank, and solar energy systems.

Nashrbo Village Water Station

Nashrbo Village Water Station

The project is a complete water station in the village. Sadagaat Charity Organization drilled a 500-meter deep underground well and installed a solar water pumping system (submersible pump and solar panels with a support structure and control switch). 

In addition to installing a 24 cubic meter GRP water tank on an iron stand of 6 meters height. 

The number of beneficiaries of the project is about 9200 residents of the village in addition to an animal wealth estimated at 6000 heads of various types of livestock.

 

Al-Eskan 9 Village (New Halfa) Water Station

Al-Eskan 9 Village (New Halfa) Water Station

The project is a tank for a water station in the village. Sadagaat Charity Organization supplied and installed a 24 cubic meter GRP water tank on an iron stand, 6 meters high, with a reinforced concrete pipe. 

The number of beneficiaries of the project is about 2000 civilians in addition to an animal wealth estimated at 500 heads of various types of livestock.

 The implementation was carried out by contractors specializing in tanks installation and civil works – 2020.

Al-Atyab Village Water Station Project

Al-Atyab Village Water Station Project

The project is a water station in the village. Sadagaat Charity Organization completed the well of the water station by installing a solar water pumping system (submersible pump and solar panels with a support structure and a control switch). In addition to maintaining the existing tank and fencing the station. 

The number of beneficiaries of the project is about 3000 beneficiaries in the village and more than 3000 beneficiaries in the neighboring villages as well as the animal wealth estimated at more than 2000 heads.

 The implementation was carried out by contractors specializing in tanks and solar energy systems.

Al-Sheikh Bilal (Al-Qaddala) Water Station

Al-Sheikh Bilal (Al-Qaddala) Water Station

The project is the completion of a village water station and an internal network. Sadagaat Charity Organization installed a solar water pumping system (submersible pump and solar panels with a support structure and a control switch). 

In addition to the village’s internal water network, with 4-inch diameter HDPE pipes, with a total length of 350 meters. 

The number of beneficiaries of the project is about 2,400 residents of the village in addition to an animal wealth estimated at 2,000 heads of various types of livestock. 

 The implementation was carried out by contractors specialized in solar energy systems and transmission lines.